Big Digital Acquires Hood County Site for AI Data Center Expansion

Big Digital Energy has completed the acquisition of a power-ready industrial site in Hood County through a joint venture with 10NetZero, advancing plans for a large-scale AI and high-performance computing campus that could ultimately support up to 300 megawatts of power.

Potential for 300 MW campus

Big Digital Energy announced it has completed the acquisition of a previously announced industrial site in Hood County, Texas, through a joint venture with energy infrastructure company 10NetZero.

Located less than 40 miles from the Dallas-Fort Worth metroplex, the approximately 50-acre property currently has 17 megawatts (MW) of operational power.

According to Big Digital, the site's existing natural gas infrastructure could support behind-the-meter power generation, allowing the campus to eventually reach up to 300 MW of total capacity.

The company has also retained Northland Capital Markets as its financial advisor to evaluate artificial intelligence and high-performance computing (HPC) opportunities for the property, including financing options and partnerships with potential customers.

Company plans next phase.

Big Digital CEO Phil Stanley said securing ownership of the property moves the project into its next state of development.

Phil Stanley: "Completing this acquisition is an important step in building Big Digital's AI Infrastructure platform and moves the Hood County project from a prospective opportunity to a controlled, powered development asset."

Development Plans

Big Digital and 10NetZero said they will begin advancing:

  • Site planning and engineering.
  • Customer engagement.
  • Data center development activities.
  • Power expansion planning.

The companies said additional updates will be provided as major development milestones are reached.

The Bottom Line

Big Digital Energy has completed its acquisition of a Hood County development site, giving the company control of a strategically located property that could ultimately support up to 300 MW of power for AI data centers and other high-performance computing applications.

Raeylee Barefield

Raeylee Barefield is a Legislative Correspondent based in Austin, Texas, specializing in state government and public policy. With one year of reporting under her belt, she covers legislative developments, committee hearings, and policy debates. She has been cited by Texas Politics and Big Energy for her coverage and analysis of legislative and regulatory issues. Her reporting typically focuses on Public policy, Stare government, environmental policy, and energy regulation. To contact her, please reach out at Raeylee@dnm.news

Recent Posts

Jupiter Power Secures $1.4 Billion for 10 Battery Storage Projects

Jupiter Power announced $1.4 billion in financing across four transactions supporting 10 utility-scale battery energy…

1 day ago

Sessions and Hoyer Introduce Bill to Modernize AbilityOne Program

Representatives Pete Sessions (R) and Steny H. Hoyer (D-MD) introduced bipartisan legislation to update the…

1 day ago

Water Resources Bill Passes the House With Houston Flood Protection Provision

The House of Representatives voted unanimously this week to pass the bipartisan Water Resources Development…

2 days ago

Dan Crenshaw Warns Data Center Opposition Could Hurt U.S. AI Leadership

U.S. Representative Dan Crenshaw (R) argued that opposition to artificial intelligence data center development could…

2 days ago

Ken Paxton Clarifies Law Enforcement Agencies That Can Receive Child Abuse Reports

Texas Attorney General Ken Paxton (R) issued a formal opinion clarifying which law enforcement agencies…

2 days ago

Senate Advances Ted Cruz’s Protect College Sports Act

The U.S. Senate voted 74-24 to advance Senator Ted Cruz’s (R-TX) Protect College Sports Act,…

2 days ago