A federal court ruling has thrown the future of Sentinel Midstream's $2.1 billion Texas GulfLink crude oil export project into uncertainty, potentially putting its offshore construction plans and federal operating license at risk.

The 5th U.S. Circuit Court of Appeals vacated a federal approval underpinning the project, finding that the Maritime Administration (MARAD) violated the Deepwater Port Act by approving an application area that overlapped with Enterprise Products Partners' Sea Port Oil Terminal project.

The decision took effect Oct. 30. Environmental group Better Brazoria Clean Air and Water, which petitioned the court, says MARAD must now suspend or revoke GulfLink's license because the ruling invalidated the record decision supporting it.

"The Court's decision is clear: it vacated the record of decision that was the foundation of GulfLink's license," said Michael Brown, counsel for the petitioners.

Sentinel disputes the suggestion that the project had stopped. Senior Vice President Bruce Heine told Reuters that the company remains on track to begin operations in the fourth quarter of 2028, with construction and site improvements continuing at its Jones Creek terminal near Freeport.

Heine said Sentinel has purchased major equipment and pipeline materials and secured key construction contracts. The company also said multiple options remain available to address the court's concerns without disrupting its schedule.

However, Sentinel acknowledged in an earlier court filing that vacating the approval exposed its license to possible suspension or revocation and could prevent construction of the offshore components. The company said it would not begin deepwater port construction under the existing regulatory circumstances and plans to petition the U.S. Supreme Court.

MARAD said it was disappointed by the ruling and is pursuing options to advance the administration's energy agenda.

The decision could reach beyond GulfLink. Sentinel warned that two other pending deepwater port applications have similar boundaries and may require redesignation, potentially creating additional delays.

Raeylee Barefield

Raeylee Barefield

Raeylee Barefield is a Legislative Correspondent based in Austin, Texas, specializing in state government and public policy. With one year of reporting under her belt, she covers legislative developments, committee hearings, and policy debates. She has been cited by Texas Politics and Big Energy for her coverage and analysis of legislative and regulatory issues. Her reporting typically focuses on Public policy, Stare government, environmental policy, and energy regulation. To contact her, please reach out at [email protected]

Related Posts

Leave a Reply

Your email address will not be published. Required fields are marked *

Subscribe to the newsletter everyone in Texas is reading.

This field is for validation purposes and should be left unchanged.
The Floridian
Cactus Politics
Big Energy News
Dome Politics
Northeast Independent
Our Privacy Policy has been updated to support the latest regulations.Click to learn more.×